The schedule, as summarized from the notice below, is as follows:
July 21, 2025: Eastbound traffic on Lakeshore Rd. E. will be reduced to a single lane from Hydro Road to Orchard Rd. The bicycle pathway parallel to Lakeshore Rd. will be diverted onto the roadway, isolated from motorists.
July 26, 2025: Westbound traffic on Lakeshore Rd. E. will be reduced from a single lane from Hydro Rd to Orchard Rd. No traffic (with exception of emergency vehicles) will be able to access Lakeshore Rd. E. from Haig Blvd. A detour will be set-up to advise motorists where to travel.
July 27, 2025: Westbound traffic to be reinstated
August 1, 2025: Eastbound traffic, including bicycle pathway, to be reinstated