Clarke Memorial Hall Restoration Project

By April 30, 2026Construction, Ward 1
Clarke Hall will be undergoing important restoration and repair work beginning in early May.
This project will help preserve the building’s heritage character while addressing key infrastructure needs.

The scope of work for this project includes the following:

  • Heritage restoration of windows and masonry walls
  • Replacement of the main front exterior stairs and two (2) rear exterior exit stairs
  • Replacement of electrical panels and disconnect switches
  • Structural repairs to the building foundations

The contractor is scheduled to mobilize in early May. All work associated with this project is anticipated to be completed by the end of fall.

To accommodate foundation and stair work, the following building entrances will be temporarily closed:

  • North front entrance: Closed from May to mid-August
    • The southwest entrance will be used as the alternate access during this period.
    • The sidewalk in front of the building will also be closed, with signage in place to redirect pedestrian traffic.
  • Rear south exit stairs: Closed from mid-August to mid-October

Access to the building for existing bookings will be maintained at all times; however, booking capacity will be restricted during construction due to ongoing work at building entrances and exits. Recurring weekly bookings already in place will continue to operate from the facility.

Communications by the Recreation team to existing bookings/user groups have gone out via email and telephone to inform them about the construction project. Additionally, Recreation will continue to communicate out to existing bookings/user groups during construction the exact entrance closure dates and Construction Fire Safety Plan.

The Recreation team will redirect any additional or special event bookings requiring larger capacities to nearby facilities for the duration of the construction period. Full, normal-capacity bookings are expected to resume starting November 2026.