SCHEDULED WATER SUPPLY INTERRUPTION NOTIFICATION
RELATED TO CAPITAL WORKS CONSTRUCTION

INTERRUPTION DETAILS
Date: Tuesday February 13th, 2024
Time: Brief interruptions between 7:30 a.m. to 12:00 p.m.
Location: 1684, 2206, 2215 and 2220 Dundas Street East
Ward 1 and 3, City of Mississauga
Affecting: Approximately 4 Commercial/Industrial Units affected
Project No.: 18-1310 C
Project Manager: Brandon Vandermeer
Telephone: (647) 824-9821

February 8, 2024
Project 18-1310 C

The Peel Region Public Works department regularly maintains and repairs the water system to make sure you have a consistent supply of quality drinking water. Sometimes we must turn off your water supply while work on the system or conduct tests.

On Tuesday February 13th, 2024, between 7:30 a.m. and 12 p.m., please expect a loss of water pressure and a brief water outage (roughly 15 minutes) while we work in your area. If we need to reschedule this work due to weather or other circumstances, we will let you know the new date and time.
If this interruption may affect an alarm or maintenance company, it is your responsibility to notify them.

Property owner/manager responsibilities during a water interruption
If you are a property owner/manager, it is your responsibility to:
• Ensure maintenance, mechanical or plumbing staff are on site during the water interruption, as it may affect internal systems that rely on water such as boilers, fire suppression, and alarms.
• Notify the fire alarm company if the interruption could affect an alarm system.
• Have a fire watch completed during the water interruption, as the building’s sprinkler protection system will not function when the water supply is shut off.

After the water interruption
When we turn the water back on, air in the pipes may make the water cloudy and your plumbing may vibrate or make noise. We recommend removing the air by slowly turning on your taps from the lowest to the highest faucet in the building (that is, starting in the basement/first floor, and finishing on the top floor). You will likely need to run the water for 10 to 30 seconds. Run the water until it is clear, and any vibration or noise has stopped.

Important note
After the water is turned back on, we recommend checking the water meter (usually located in the basement). If it is leaking, call Water Meter Installations Dispatch at:
• 905-791-7800, extension 3226 (8:30 a.m. to 4:30 p.m. – Monday to Friday)
• 905-791-7800 extension 4409 (after hours or statutory holidays)

Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices. Visit peelregion.ca/construction/signup to start signing up.

Keeping you informed
We will let you know if there are any major changes to the plans.
Information on this project can also be found at peelregion.ca/pw/construction/miss/18-1310C.asp

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water.
If you have any questions, please contact us.

Water Linear Engineering