UPDATE Message from AMICO – Temporary Closure of Haig Blvd at South Service Road

By June 9, 2022October 26th, 2023Issues, Resources, Ward 1

Monday, June 13th, 2022, to late summer, 2024

Haig Boulevard will remain closed till late summer 2024 to complete sanitary sewer construction in the Spring of 2024.

What work is taking place?

Construction crews will be working on the installation of new watermain, storm, sanitary, sidewalk, electrical, tunneling removal, grading, and paving along South Service Road at Haig Blvd from June 13th, 2022, to late summer 2024. Please note the work will be extended into 2024.

This work requires temporary closure of Haig Blvd at North Service Road. Please look for advisory signs announcing closures and detours on the roadway.

Emergency access will always be maintained.

TIMING

  • Construction will be from June 13, 2022, to late summer 2024.
  • The work hours are 7:00 am to 7:00 pm daily.
  • Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.
  • In the unlikely scenario where the work requires an extended closure, the entrance will be temporarily re-opened after work hours.

 

TRAFFIC DETAILS

  • Access to the property will be maintained through a detour via Applewood Road and Brooks Drive.
  • Watch for slow moving vehicles entering and exiting work areas.
  • Remember to reduce your speed when approaching lane reductions.

 

WHAT TO EXPECT?

  • Every effort will be made to minimize disruptions.
  • Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, and other construction equipment related to this work.

 

TRANSIT DETAILS

  • MiWay will continue to operate with regular service.
  • Watch for additional signs directing passengers at bus stops as boarding areas may be relocated.
  • A temporary pedestrian pathway will be provided to access the boarding areas.
  • Visit miway.ca/updates for updates on your bus route.

 

PEDESTRIAN DETAILS

  • Please take care when travelling near construction areas.
  • Sidewalk access in the area could be affected.
  • Watch for additional signs directing pedestrians as detours may be required.
  • Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.

 

PROPERTY DETAILS

  • Please ensure any personal belongings, such as signs, benches and underground sprinklers on city owned land have been relocated prior to the beginning of construction.
  • For details on your property boundaries, please refer to your land survey, or consult an Ontario Land Surveyor.

 

CONTACT US