What work is taking place?
Construction crews will be installing dry utilities along Hurontario Street that will also need to cross Mineola Road East. This will result in a temporary closure of a portion Mineola Road East from August 23 to August 30, 2022. The works are scheduled to take place 24 hours a day. The roadway will be closed throughout this period and there will be no access for emergency vehicles. Extended construction works from 7am until 10pm are scheduled to take place from August 31 until September 2, 2022, but the two-way traffic will be maintained on Mineola Road East.

These works follow the installation of wet utilities in July. As part of the larger sequencing of the project, the two works could not be combined. The roadway is scheduled for a closure prior to September to reduce impacts on the schools in the area.

In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, and other construction equipment related to this work. Some of this work will be done overnight and, on the weekend, so crews will be able to complete this work safely and efficiently.
MiWay Route 8-Cawthra will be affected by the closure of Mineola Road East and there will not be transit service on Mineola Road/Atwater Avenue. Instead the route will travel along Cawthra Road to Lakeshore Road. Visit www.miway.ca/updates for updates.

During this closure, motorists can access Mineola Road East from Hurontario Street using the detour map provided. Please note, work may be rescheduled due to weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.

TIMING

•Mineola Road East will be closed from:oAugust 23 to August 30, 2022oWork hours are 24 hours a day

•Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.

TRAFFIC DETAILS
•Access to Mineola Road East will be maintainedthrough a detour from Hurontario Street, PinewoodTrail, and Goldthorpe Road.
•Watch for slow moving vehicles entering and exitingwork areas.
•Remember to reduce your speed when approachingwork zones.

WHAT TO EXPECT?
•Every effort will be made to minimize disruptions.
•Residents and businesses near the work site canexpect to hear noise and vibration caused by trucks,excavators, loaders, triaxles, backhoes, and otherconstruction equipment related to this work.

TRANSIT IMPACT DETAILS
•MiWay’s Route 8-Cawthra will be on detour duringthis closure. Route 8 will not service Atwater Avenueand Mineola Road. Instead the route will travel alongCawthra Rd. to Lakeshore Rd.
•Visit www.miway.ca/updates for updates.

PEDESTRIAN DETAILS
•Please take care when travelling near constructionareas.
•Watch for additional signs directing pedestrians asdetours may be required.
•Clear and defined walking paths will be maintainedduring construction to ensure pedestrian safety

CONTACT US
•Metrolinx has a dedicated community relations teamin place to work with residents in Peel region throughthe construction and operation of thistransformational transit project.