March 2022 to late May 2022 between the hours of 8 p.m. to 4 a.m.

What work is taking place?
With the construction of the “Push Box” structure complete, construction crews will continue with micro-piling activities and the installation temporary track supports within the railway corridor at Port Credit Station near Hurontario Street. These activities are expected to continue from March 2022 to late May 2022. This critical infrastructure will allow for excavation activities to continue while the underpass structure is pushed into place with minimal disruption to train movements overhead. Once in place, the underpass will allow for light rail vehicles to enter and exit Port Credit Station. Read More